Flood door at Metro Station Kgs. Nytorv, Copenhagen
Metroselskabet, Metro Station Kgs. Nytorv, Transfer tunnel
Client: Metroselskabet Main contractor: NCC A/S Problem: Storm surge protection of transfer tunnel. In the event of water entering the metro station, flooding must be prevented in both metro stations. Solution: Design, manufacture and installation of Flood Doors that automatically close when water enters the metro during storm surges, thereby separating the two stations. Type and dimensions: Flood doors 2 x 4300×2850 Protection: for 5m column of water